140 meters limit height! XCMG XCA1800 staged a high-altitude blockbuster
|
|
"Qingfeng No. 3"
XCMG XCA1800 All Terrain Crane
Take the efficiency of a fan for an average of 2 days
Completed the extremely difficult extreme hoisting in Guangxi
Staged a blockbuster film at an altitude of 140 meters
Recently, Beijing Shenda Group, which tops the list of "China's Top 10 Wind Power Hoisting Enterprises in 2022", joined hands with XCMG XCA1800 all-terrain cranes to participate in the construction of a wind farm project in Qinzhou City, Guangxi. It is understood that this city is also the city with the most energy projects in Guangxi Autonomous Region.
The configuration data of this wind power hoisting is also "high-level": 4.65MW wind turbine, 140m hoisting height, 120 tons nacelle, 94m fan blades... Not to mention the soft soil on site, small construction site, and continuous rain caused the hoisting No matter from the key data or the objective environment, it can be seen that this is a "ceiling" project for onshore wind power hoisting.
In addition, the project is located in a mountainous area with many wind turbine sites and scattered construction sites, but the XCMG XCA1800 all-terrain crane can complete the transition of a distance of 4-5 kilometers in only 3 hours with the super-lift.
Zhang Zhaozhao, the operator of Beijing Shenda Group, said: "XCMG's 1800-ton crane has stable handling performance and excellent wind resistance, which makes the operation safety factor higher; and it has a strong traffic capacity, and there is no pressure to pass on complex road conditions on site. It can be completed within 1 day, put into operation quickly, and the efficiency is very high.”
XCMG XCA1800 is the all-terrain crane with the highest performance for 140-meter wind power installation in the world. It has set a record for the installation efficiency of 15 140-meter wind turbines in 27 days. XCMG 1,000-ton cranes are creating bright moments one after another in the history of wind power hoisting by virtue of their strong environmental adaptability, operational stability and high operational efficiency.
It is understood that after the project is fully put into operation, it is expected that the annual power generation will exceed 500 million KWH, save 219 million kilograms of standard coal, and reduce carbon emissions by 427 million kilograms, which will accumulate new kinetic energy and inject new vitality into the high-quality economic development of Qinnan District.
|
|
|
|
|
|
|
|
|
|